Summary0001033: Dependency Updates = Screwed!
DescriptionWhen changing a task start & finish date all dependencies of that task jump to the end date of the changed task.
EG
Task A changed to Start 03/01/2012 0900 and finish 1000
Task B changed automatically to start and finish at 03/01/2012 1000
Task C changed automatically to start and finish at 03/01/2012 1000

Task B is dependant on Task A and Task C is dependant on Task B

TagsNo tags attached.
duplicate of 0001000closed caseydk Issues with Task Dates with Dependencies 
Attached Filespng temp.png (189,639) 1969-12-31 16:00
https://bugs.web2project.net/file_download.php?file_id=307&type=bug
png

Notes
(0002351)
brynmoorhouse   
2011-12-13 16:05   
Either that or the date set is completely wrong, as shown in the screenshot - Task B is still in December 2010!!
(0002626)
caseydk   
2012-08-07 21:05   
Resolved: https://github.com/caseysoftware/web2project/pull/130

Please note that this solution is *only* available in the v3.0-pre development and can't be applied to any version earlier (eg 2.4, 2.3, etc).

Issue History
2011-12-13 16:02brynmoorhouseNew Issue
2011-12-13 16:02brynmoorhouseFile Added: temp.png
2011-12-13 16:05brynmoorhouseNote Added: 0002351
2011-12-23 09:08caseydkProjectv2.4 Release (Closed) => v3.0 Release
2011-12-23 09:19caseydkRelationship addedduplicate of 0001000
2012-03-17 22:30caseydkStatusnew => assigned
2012-03-17 22:30caseydkAssigned To => caseydk
2012-08-07 21:05caseydkNote Added: 0002626
2012-08-07 21:05caseydkStatusassigned => resolved
2012-08-07 21:05caseydkResolutionopen => fixed
2013-08-28 11:14caseydkFixed in Version => 3.0.0