MantisBT - Pending Requests
View Issue Details
0000804Pending RequestsGantt Chart Generationpublic2011-05-17 01:062014-08-16 18:47
Reporterckwanhu 
Assigned To 
PrioritynormalSeverityfeatureReproducibilityN/A
StatusfeedbackResolutionopen 
PlatformOSOS Version
Product Version 
Target VersionFixed in Version 
Summary0000804: Column "Progress" in the gantt Chart
DescriptionIt would be great if we could have the column progress in the gantt chart.
(after or before the Duration)

It would be greater to be able to choose the colum we want to display with checkboxes for example.
TagsNo tags attached.
Attached Files

Notes
(0001918)
caseydk   
2011-05-21 22:21   
Progress as in the percent complete?
(0001931)
ckwanhu   
2011-05-22 23:05   
Progress as in percent complete.

But Progress is the word you use in every form you have created.

Issue History
2011-05-17 01:06ckwanhuNew Issue
2011-05-21 22:21caseydkNote Added: 0001918
2011-05-21 22:21caseydkStatusnew => feedback
2011-05-21 22:21caseydkProjectv2.3 Release (Closed) => Pending Requests
2011-05-22 23:05ckwanhuNote Added: 0001931
2014-08-16 18:47caseydkCategoryGeneral => Gantt Chart Generation