View Issue Details [ Jump to Notes ] | [ Issue History ] [ Print ] | ||||||||
ID | Project | Category | View Status | Date Submitted | Last Update | ||||
---|---|---|---|---|---|---|---|---|---|
0001476 | v3.2 Release | Tasks | public | 2014-04-06 01:20 | 2014-07-16 21:27 | ||||
Reporter | opto | ||||||||
Assigned To | caseydk | ||||||||
Priority | normal | Severity | major | Reproducibility | have not tried | ||||
Status | closed | Resolution | unable to reproduce | ||||||
Product Version | |||||||||
Target Version | 3.2 | Fixed in Version | 3.2 | ||||||
Summary | 0001476: task gantt broken | ||||||||
Description | undefined variable where | ||||||||
Tags | No tags attached. | ||||||||
Attached Files |
|
![]() |
|
caseydk (administrator) 2014-04-06 12:20 |
What line are you getting the error on? I'm not seeing similar.. |
opto (manager) 2014-04-06 12:50 |
it's inside the gannt symbol we see if there are no tasks in a new project |
caseydk (administrator) 2014-05-25 20:42 |
I still can't reproduce this one regardless of how many tasks I have. If you're still seeing it, please let me know. Otherwise, I'm considering it closed at the end of this week. |
![]() |
|||
Date Modified | Username | Field | Change |
---|---|---|---|
2014-04-06 01:20 | opto | New Issue | |
2014-04-06 12:20 | caseydk | Note Added: 0003294 | |
2014-04-06 12:20 | caseydk | Assigned To | => caseydk |
2014-04-06 12:20 | caseydk | Status | new => feedback |
2014-04-06 12:50 | opto | Note Added: 0003296 | |
2014-04-06 12:50 | opto | Status | feedback => assigned |
2014-04-13 18:50 | caseydk | Target Version | => 3.2 |
2014-05-25 20:42 | caseydk | Note Added: 0003390 | |
2014-05-25 20:42 | caseydk | Status | assigned => feedback |
2014-06-02 22:19 | caseydk | Status | feedback => resolved |
2014-06-02 22:19 | caseydk | Resolution | open => unable to reproduce |
2014-07-16 21:26 | caseydk | Fixed in Version | => 3.2 |
2014-07-16 21:27 | caseydk | Status | resolved => closed |