View Issue Details [ Jump to Notes ] | [ Issue History ] [ Print ] | ||||||||
ID | Project | Category | View Status | Date Submitted | Last Update | ||||
---|---|---|---|---|---|---|---|---|---|
0001555 | v3.2 Release | Tasks | public | 2014-05-27 06:14 | 2014-07-16 21:29 | ||||
Reporter | opto | ||||||||
Assigned To | caseydk | ||||||||
Priority | normal | Severity | crash | Reproducibility | have not tried | ||||
Status | closed | Resolution | fixed | ||||||
Product Version | |||||||||
Target Version | 3.2 | Fixed in Version | 3.2 | ||||||
Summary | 0001555: admin can't see task his secretary owns | ||||||||
Description | admin has rights for everything. Also exolicitly got all rights on that specific project. Result: tasks per user for secretary shows task 'bbbb' (owned by her, admin not assigned). project view does not show task 'bbbb' to admin. In my opinioun, that is a very serious bug. Or did I oversee something in permissions? (both are same company) project list mentions 14 tasks, project view only shows 7 tasks | ||||||||
Tags | No tags attached. | ||||||||
Attached Files |
|
![]() |
|
caseydk (administrator) 2014-05-29 11:22 |
I've updated the admin permissions check to make sure Admins can really view everything they're expecting to. The patch is here: https://github.com/web2project/web2project/commit/85f8feb06b8b7ada64c1f178da3bcc093ba47fc8 |
![]() |
|||
Date Modified | Username | Field | Change |
---|---|---|---|
2014-05-27 06:14 | opto | New Issue | |
2014-05-29 11:22 | caseydk | Note Added: 0003403 | |
2014-05-29 11:22 | caseydk | Status | new => resolved |
2014-05-29 11:22 | caseydk | Resolution | open => fixed |
2014-05-29 11:22 | caseydk | Assigned To | => caseydk |
2014-06-10 22:09 | caseydk | Target Version | => 3.2 |
2014-07-16 21:26 | caseydk | Fixed in Version | => 3.2 |
2014-07-16 21:29 | caseydk | Status | resolved => closed |