View Issue Details [ Jump to Notes ] | [ Issue History ] [ Print ] | ||||||||
ID | Project | Category | View Status | Date Submitted | Last Update | ||||
---|---|---|---|---|---|---|---|---|---|
0001716 | v3.4 Release (Current) | Projects | public | 2016-10-26 04:10 | 2019-01-03 12:53 | ||||
Reporter | opto | ||||||||
Assigned To | opto | ||||||||
Priority | normal | Severity | minor | Reproducibility | have not tried | ||||
Status | closed | Resolution | fixed | ||||||
Product Version | |||||||||
Target Version | Fixed in Version | ||||||||
Summary | 0001716: Subproject: no token task created for parent project | ||||||||
Description | Subproject: no token task created for parent Project or it is broken and not visible for some reason | ||||||||
Tags | No tags attached. | ||||||||
Attached Files |
|
![]() |
|
opto (manager) 2016-10-26 04:10 |
this happens in the following workflow: set system config to check for task dates create parent project create subproject now, no token task is created because token task is deemed invalid (missing dates). either system config must be set not to check for dates, or there must be tasks already entered. I think this clearly is a bug, the token task should always be created, even if no dates, otherwise this would be very confusing (sometimes it is created, sometimes not) |
caseydk (administrator) 2019-01-03 12:53 |
In the 31 Dec 2018 release: http://docs.web2project.net/release-notes/3.4.html |
![]() |
|||
Date Modified | Username | Field | Change |
---|---|---|---|
2016-10-26 04:10 | opto | New Issue | |
2016-10-26 04:10 | opto | Note Added: 0003790 | |
2016-10-26 04:10 | opto | Status | new => resolved |
2016-10-26 04:10 | opto | Resolution | open => fixed |
2016-10-26 04:10 | opto | Assigned To | => opto |
2016-10-26 04:10 | opto | Project | v3.3 Release => v3.4 Release (Current) |
2019-01-03 12:53 | caseydk | Note Added: 0003971 | |
2019-01-03 12:53 | caseydk | Status | resolved => closed |